- 100 per cent of actions achieved or partially achieved
- 79 per cent of performance indicators either met or exceeded target
- 96 per cent of available performance indicators have either maintained or showed improvement on previous years
- completed 97 per cent of service requests for missed bins within five working days (target was 92 per cent)
- achieved 76 per cent customer satisfaction levels with customer hub contacts (target was 65 per cent)
- paid 96 per cent of invoices within 30 calendar days (target was 90 per cent)
- achieved 18,190 outdoor leisure bookings (target was 16,000)
- planted 750 linear metres of hedging (target was 500 metres)
- supported 42 businesses (existing Belfast Business Promise members) to improve their recognition level (target was 10)
- occupied 24 previously vacant citywide properties through the Vacant to Vibrant intervention (target was 20)
- progressed 220 projects under the Physical Programme (target was 100)
- processed 87 per cent of planning enforcement cases within 39 weeks – exceeding the statutory 70 per cent target)