Table 4: Key stages in securing a Travel Plan for new development


 
StageActivity
Planning ApplicationScoping
  • Applicant establishes the need for a Transport Assessment (TA) and Travel Plan (TP) through reference to the thresholds, criteria set down in policy and guidance and other local circumstances.
  • Applicant, authority and DfI agree the type of travel plan required - travel plan statement, framework, interim, as appropriate.
  • Applicant agrees the requirements for the TA/TP with the Council and DfI and exchange contact details.
  • Applicant and authority agree how the TA/TP are to be integrated; establish and agree any baseline data, key outcomes sought and assumptions to be used if appropriate.
Pre-application discussions
  • Applicant submits draft TA/TP for initial evaluation by the Local Authority and DfI.
  • Both the Authority and DfI give feedback to applicant to enable review of the assessment and travel plan.
  • Applicant and Planning authority undertake negotiations, including the local highway/ transport authority and others who will be party to any legal agreements, such as DfI and transport operators.
  • Local Authority and applicant agree draft terms of legal agreement and extent of any conditions if appropriate.
Submission
  • Developer submits final transport assessment, Travel Plan with planning application.
  • Authority carries out further/final evaluation of plan to determine its ‘fitness for purpose’.
  • Planning authority undertake statutory consultation.
  • Authority, DfI and applicant agree any amendments to the travel plan and legal agreement and finalise supporting documentation. If an interim Travel Plan, an approved legal agreement should include timing of full travel plan and include a clause that interim travel plans are written within six months of occupation of the development.
Determine planning application and grant planning permission
Post- determination of planning application and pre-occupation
  • Lead authority to enter details of travel plan into database, including contact details. This should link to any development control and Section 76 monitoring.
  • Authority to ensure collection of baseline data required for monitoring from applicant on pre-determined standardised format.
  • Developer/occupier commences implementation of measures, including completing a full travel plan where relevant.
Occupation
  • Occupier/developer ensures full implementation of travel plan, including completion of full travel plan where relevant.
  • Authority agrees that travel plan requirements (especially implementation of agreed measures) have been met to enable occupation to take place, based on information provided by occupier/developer.
  • Authority checks that all necessary data prior to occupation have been collected.
  • Authority and developer/occupier agree any necessary handover of responsibilities for developer to occupier.
MonitoringPost-occupation
  • Occupier (or agent) monitors travel plan outcomes as set out in a planning condition or agreement (in conjunction with the local authority if appropriate and agreed) and in line with authority’s requirements.
  • Occupier or other approved party (in partnership with local authority where appropriate and agreed) collects data at appropriate times in agreed form.
  • Authority ensures any ongoing measures continue to be delivered.
  • Occupier and authority undertake review process to agreed timescales:
    • If outcomes agreed and in line with targets, continue to monitor;
    • If outcomes not in line with targets, considers amendments to plan.
 Default
  • Local Planning Authority in consultation with authority leading on travel plan measures considers use of default mechanisms in outcomes not delivered and amendments cannot be agreed with developer/occupier.