20.1 The Contractor shall not sub-contract or transfer, assign, charge, or otherwise dispose of the Contract or any part of it without the prior written consent of the Council.

20.2 The Contractor shall ensure that any sub-contractor complies with the terms and conditions of the Contract, so far as they are applicable. Any sub-contract shall not relieve the Contractor of his obligations under the Contract.

20.3 Where the Contractor enters into a contract with a supplier or sub-contractor for the purpose of performing the Contract or any part of it, he shall cause a term to be included in such contract which requires payment to be made by the Contractor to the supplier or subcontractor within a specified period not exceeding 30 days from receipt of a valid invoice as defined by the Contract requirements.