39. Rise and fall price provisions

39.1 Subject to condition 9, the Contract Price shall remain fixed during the initial period.

39.2 If the Council exercises the option to extend the Contract as per condition 3.3 then the following shall apply:

39.2.1 If by reason of any rise or fall in the costs (ruling at the time of tender) of materials, labour, transport or the carrying out by the Contractor of his statutory obligations, the cost to the Contractor of performing his/its obligations under the Contract shall be increased or reduced, the amount of such increase or reduction shall be added to or deducted from the price quoted in the tender documents, as the case may be, provided that no account shall be increased by the default negligence or omission of the Contractor;

39.2.2 The Contractor shall only be entitled to one price increase for each year of the remainder of the Contract period and any subsequent period arising from the Council having exercised its option to renew the Contract and any price increase shall be in line with the Consumer Price Index.

39.2.3 All requests for a price increase must be made in writing by the Contractor and sent to the Council’s Procurement Manager not less than two months prior to the expiry of the first year of the Contract period and thereafter not less than two months before each anniversary of the commencement date of the Contract period (and any subsequent period applicable).

39.2.4 Any price increase request under this condition shall not be admissible unless the aforementioned provision is adhered to and unless the Contractor shall within 28 days of being requested to do so, furnish such evidence as the Council shall reasonably require substantiating the claim.